File #: ID# 25-3497    Version: 1 Name:
Type: Action Item Status: Consent Agenda
File created: 7/1/2025 In control: City Council
On agenda: 7/15/2025 Final action:
Title: iv. Consider approving a contract with Southern Striping Solutions, LLC in the amount of $1,371,949.79 for the Periwinkle Way Milling and Resurfacing Project and authorize the City Manager to execute the contract. Funds are available for these construction services through a combination of a Florida Department of Transportation (FDOT) Grant 454841-1 and Florida Department of Environmental Protection (FDEP) Grant HA017.
Attachments: 1. Agenda Memorandum, 2. Contract, 3. Bid Opening Information 6-26-25, 4. Southern Striping Solutions LLC Proposal, 5. Sanibel Periwinkle Way Project Manual, 6. Sanibel Periwinkle Way Plans
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

iv.   Consider approving a contract with Southern Striping Solutions, LLC in the amount of
      $1,371,949.79 for the Periwinkle Way Milling and Resurfacing Project and authorize the City
      Manager to execute the contract.  Funds are available for these construction services through a
      combination of a Florida Department of Transportation (FDOT) Grant 454841-1 and Florida
      Department of Environmental Protection (FDEP) Grant HA017.